Week of October 8, 2007 Street Construction Within The City of Hattiesburg
Resurfacing North 21st from Quinn to West 4th Street
Resurfacing Venetian Way from North 21st Avenue to Shelly Place
Resurfacing Shelly Place south of West 4th Street
Resurfacing South 27th Avenue from Hardy Street to Camp
Resurfacing O'Ferrell Street from US Highway 49 to South 28th Avenue
Resurfacing Camp Street from US Highway 49 to South 27th Avenue
Installing storm drains along Ross Blvd from Hardy Street to Pearl Street
Replace sewer line on Capital Street between Xavier & Broad Street
Drainage work Lurlyne & McCall
Installing sewer on 1st Avenue from McInnis Springs to Clementine
Replacing sewer lines on Stanley Street from Highway 42 to Mildred Street
Bennie J. Sellers, P.E., P.L.S., Director of Public Services
601-545-4540